Update Estimate FTE Hours
The Updating Estimate FTE Hours utility updates all open Estimates to reflect update FTE hour calculations when changes to the Financial Month Calendar occur. Without this utility, each Estimate would have to be updated individually to reflect the updated FTE hour calculations.
Availability
Only Users with the Task Estimating Administrator Permission will have access to this function.
Navigation
Modules > Estimating > Utilities > Update Estimate FTE Hours
Page Elements
The Update Estimate FTE Hours page has the following page elements:
- Status Codes to Update
- Lists the available Estimate Status Codes you can select for updating FTE Hour calculations
- Estimates to Update
- The number of Estimates that will be updated, based on the selected Status Codes
How to Update Estimate Rates
- Select one or more Estimate Status Codes that you want to include in the Update process
- As you select/deselect Status Codes, the Estimates To Update indicator will change
- Click the Update All Estimate FTE Hours Now button to refresh all FTE Hour calculations in all Estimates that match the selected Status Codes
- Clicking Cancel will bring you back to the Estimate Utilities menu.
The Update Estimate FTE Hours utility.