NASA Contractor Estimate Report
The NASA Contractor Estimate Report displays current Actual Costs, Planned Costs for the next Financial Month, and Estimate at Completion data.
Navigation
Modules > Financials > Agency Reporting > NASA Contractor Estimate Report
Page Elements
Report Header
- Report Title
- Report Type (Contractor Estimate Report)
- Selected Financial Month and corresponding dates
- Date that Actuals data was last updated
An example of a Contractor Estimate Report Header.
Contractor Estimate Report Elements
- Task Name
- Clicking a specific Task will lead you to the NASA Form 533M Viewer for that specific task.
- Actual Monthly Cost
- Found on the 533M form in Column 7a
- Planned Cost
- Found on the 533M form in Column 8a
- Estimate at Completion
- Found on the 533M form in Column 9a
An example a Contractor Estimate Report.
Page ID:2053-8371-8770